STH 107 (Main St) Construction Update

August 5: No access to STH 107 (Main St) from: • 1st St • 3rd St • 5th St • 6th St
Access remains open from: • North St • 2nd St • 4th St • 7th St • 8th St
August 10-17: All parking on STH 107 (Main St), including parking lanes, will be closed for paving operations.
Please plan accordingly and thank you for your patience!

WIS 107 Improvements

  • Resurface existing
  • Upgrade pedestrian curb ramps
  • Repair deteriorated storm sewer structures
  • Addition of right turn lane from County NN/4th St to north bound WIS 107

Schedule

  • Work is planned to begin June
  • Curb ramps and storm sewer improvements will take until late July at which point milling and paving operations will begin.
  • Work is anticipated to be completed in the later part of
  • The schedule is dependent on favorable weather conditions and construction

 

WIS 107 Traffic Impacts

  • WIS 107 will be open to through traffic during
  • County NN intersection improvements will be staged to maintain traffic movements.
  • Pedestrian curb ramp replacements will be staged and use temporary pedestrian accommodations or

 

During construction, landowners will be notified of any temporary impacts to driveway access ahead of time by WisDOT’s contractor. Residents’ mailboxes will be impacted by the grading work, please work with your post office to arrange mail delivery. If mailboxes are in place at the time the contractor needs to work in the area, they will remove it and place it on your property,

 

Website and Updates

 

In This Together

WisDOT recognizes businesses located in work zones have special needs. It’s critical that customers have access to businesses and that they continue to visit them, regardless of any road work inconvenience.

WisDOT’s In This Together program is offered to business and community leaders as an idea source as they plan for road construction in their area. More information is available at https://wisconsindot.gov/together.

 