DETOUR ALERT
4th St between Main and Market is set to close on Friday, June 12th
Closure is scheduled to last about a month as crews work to create a right turn lane from 4th St (County Road NN) to north bound Highway 107
Traffic heading west to 107 will be detoured north on Market St and west on 3rd St out to 107
Car traffic wishing to head east will have to take a different side road.
SEMI TRAFFIC HEADING EAST TO MARATHON CHEESE WILL BE DETOURED EAST ON 2ND STREET TO CHESTNUT ST FOR DELIVERIES OFF 4TH ST – PLEASE SEE ATTACHED MAP
Marathon Cheese Delivery Detour Route
WIS 107 Improvements
- Resurface existing
- Upgrade pedestrian curb ramps
- Repair deteriorated storm sewer structures
- Addition of right turn lane from County NN/4th St to north bound WIS 107
Schedule
- Work is planned to begin June
- Curb ramps and storm sewer improvements will take until late July at which point milling and paving operations will begin.
- Work is anticipated to be completed in the later part of
- The schedule is dependent on favorable weather conditions and construction
WIS 107 Traffic Impacts
- WIS 107 will be open to through traffic during
- County NN intersection improvements will be staged to maintain traffic movements.
- Pedestrian curb ramp replacements will be staged and use temporary pedestrian accommodations or
During construction, landowners will be notified of any temporary impacts to driveway access ahead of time by WisDOT’s contractor. Residents’ mailboxes will be impacted by the grading work, please work with your post office to arrange mail delivery. If mailboxes are in place at the time the contractor needs to work in the area, they will remove it and place it on your property,
Website and Updates
- A project website is available here: North Central – 511 WI Projects
- Weekly Road Construction updates are available online at: https://projects.511wi.gov/wis107marathoncity/
In This Together
WisDOT recognizes businesses located in work zones have special needs. It’s critical that customers have access to businesses and that they continue to visit them, regardless of any road work inconvenience.
WisDOT’s In This Together program is offered to business and community leaders as an idea source as they plan for road construction in their area. More information is available at https://wisconsindot.gov/together.
Project Contacts
- On-site Project Engineer: Blake Elsinger, (715) 572-3666 or elsinqer@guestllc.biz
- WisDOT Project Manager: Korey Boehm, (715) 459-2943 or korey.boehm@dot.wi.gov
- WisDOT North Central Region Communication Manager: Bryan Rose, (715) 493-3710 or bryan.rose@dot.wi.gov